BizNis Africa
Latest News
Pension fund investment key to addressing inequality in South Africa
Ahead of the 2017 Worker’s Day, Romeo Makhubela, Novare...
Nuclear Industry Association of South Africa reacts to High Court Judgement
The Nuclear Industry Association of South Africa (NIASA) has...
Thapelo Tsheole
Thapelo Tsheole is a seasoned Financial Markets expert with...
Nkomati Mine: Norilsk Nickel issues legal proceedings against Botswana Government
Norilsk Nickel has served notice that it intends to...
Côte D’Ivoire’s Minister of Economy to open SWIFT African Regional Conference in Abidjan
SWIFT announces today, 28 April 2017, that the Minister...
Top five money mistakes retirees must avoid
Retirement planning is an ongoing process; in fact once...
Pius Muchiri
He is the Managing Director and CEO of Nabo...
Taslim Ngom
Taslim Ngom, born in Senegal, is affiliated with real...
Forbes Woman Africa launches its first television show
FORBES WOMAN AFRICA (www.ForbesAfrica.com), the continent’s first-ever women’s interest...
Shedding light on the African shadow economy
The Informal Economy, or if you have a penchant...

Matshela Koko, Eskom Interim Group Chief Executive Officer

Eskom is pleased to announce that Unit 5 at its Medupi Power Station Project in Lephalale, Limpopo, has attained Commercial Operation status.

The unit was officially declared commercial after the completion of control performance and the 72-hour reliability tests, putting all performance guarantees to effect.

Unit 5 was first synchronised to the national grid on 8 September 2016.

This was then followed by further testing and optimising which resulted in its full power of 800 MW being attained on 17 December 2016.
This milestone came ahead of the scheduled time line of March 2018.

With an output of 800 MW going to the national grid, Unit 5 joined its sister unit, Unit 6, which has been contributing to the balancing of electricity supply and demand since 23 August 2015.

The remarkable progress came after intensive continuous testing activities and shared dedication from Eskom and its execution partners.

“The Eskom new build programme is meant for strengthening the electricity supply, Medupi with its second unit coming online, is a reflection of the endeavours towards realising this initiative, Eskom applauds the Medupi team, this milestone is indeed an epitome of delivery,” says Matshela Koko, Interim Group Chief Executive Officer.

Commercial Operation status ensures technical compliance to statutory, safety and legal requirements. This signatory milestone marks the contractual handover of the unit from the primary contractors to Eskom, which means that Medupi Unit 5 is now part of the Eskom Generation fleet.

Leave a Reply

Ver peliculas online

Fill in your details below and we will secure you a free test drive, delivered to you.

Fill in your details below and we will secure you a free test drive, delivered to you.

%d bloggers like this: